Runway 5-23 Rehabilitation Project

Airport Reopened to Fixed Wing Traffic as of 1800L on August 30, 2025

Phase XI

Overview

Phase XI has been completed.


Timing

2200L on 7.27.25 through 08.30.25

34 days to complete work

Airfield Impacts

  • Runway was 5-23 closed for entirety of Phase XI (34 days)
  • Airport was closed to fixed-wing traffic for six days during Runway 5-23 and 13-31 intersection work

Photos above were taken between August 1 and August 18 at various stages of construction.

MMU News & Updates

Phase XI Complete; Airport Reopened to Fixed Wing Traffic 1400 656 MMU | Morristown Airport New Jersey | General Aviation Airport

Phase XI Complete; Airport Reopened to Fixed Wing Traffic

Please check NOTAMs before flying into the airport

Instrument Landing System Returned to Service 1400 933 MMU | Morristown Airport New Jersey | General Aviation Airport

Instrument Landing System Returned to Service

Runway 23 ILS back in service as of April 2, 2025

Morristown Airport Statement on JSX Service 1280 960 MMU | Morristown Airport New Jersey | General Aviation Airport

Morristown Airport Statement on JSX Service

JSX service canceled at Morristown Airport as of January 7, 2025

Runway 5-23

Rehabilitation Project

Over the next 5-7 years, MMU will continue a major rehabilitation project for Runway 5-23. Separated in annual stages to minimize operational impacts, Phase X was completed in November, 2024. Work included extending the runway 5 safety area in preparation for a new localizer and EMAS. Phase XI details will be shared in the first quarter of 2025.

Planning for the RWY 5-23 rehabilitation project began in 2005, and DM AIRPORTS, LTD. (Operators of Morristown Airport), has been diligently working alongside engineering firms, the Federal Aviation Administration, and Airport Tenants to ensure a seamless flight experience for all who fly with MMU

Overall Benefits of the Runway 5-23 Rehabilitation Project at MMU once completed:

  • Brand new paved surface
  • Upgraded approach systems
  • Enhanced safety areas
  • Lighting upgrades
  • And more!

With these updates, MMU will continue to shine as a premier general aviation airport for the New York Metro Airspace, State of New Jersey, and Morris County.

Previous Phases

Phase X

Completed

Phase X was completed in November, 2024. Work included extending the runway 5 safety area in preparation for a new localizer and EMAS.

Phase IX

Completed

Phase X was completed in November, 2024. Work included extending the runway 5 safety area in preparation for a new localizer and EMAS.

Phase VIII

Completed

Phase X was completed in November, 2024. Work included extending the runway 5 safety area in preparation for a new localizer and EMAS.

Phase VII

Completed

Phase X was completed in November, 2024. Work included extending the runway 5 safety area in preparation for a new localizer and EMAS.

Phase VI

Completed

Phase X was completed in November, 2024. Work included extending the runway 5 safety area in preparation for a new localizer and EMAS.

Follow Us to Get All Notifications

Stay on the Radar

Organization
This field is for validation purposes and should be left unchanged.
MMU | Morristown Airport New Jersey | General Aviation Airport