Runway 5-23 Construction Updates

Runway 5-23 Construction Updates

Runway 5-23 Construction Updates 2560 1013 Morristown Airport

Runway 5-23 Construction: July 15th Update

Phase II, Stage B Construction of our Runway 5-23 Rehabilitation Project is well underway. Crews have begun access road construction, conduit boring for a new JCP&L power line and installation of storm water treatment devices.

The severe weather we have been experiencing this month has had minor impacts on the progress. Contractors and crews are monitoring the weather and taking advantage of good weather days to make up lost time as much as possible. While there are no significant impacts to the overall schedule as of today, July 15th, we want to remind everyone that the overall schedule is subject to change if the weather dictates.

Access road construction and boring work for the JCP&L line will continue the week of July 19th, causing the Runway 5-23 closures listed below:

Upcoming nightly-closures of Runway 5-23*

July 16: 2200L – 0600L
July 19: 2200L – 0600L
July 20: 2200L – 0600L
July 21: 2200L – 0600L
July 22: 2200L – 0600L
July 23: 2200L – 0600L

*Closures are subject to change due to weather


For full details on Phase II, Stage B construction, and an overview of the complete Runway 5-23 Rehabilitation Project, please click here to be directed to our Improving MMU web page.

MMU | Morristown Airport New Jersey | General Aviation Airport