Starting in 2018, Morristown Airport will undergo a series of capital improvement projects around the airfield. These improvements will include runway work, lighting system upgrades, runway safety area improvements and more.

All of these improvements are aimed towards giving users of MMU the best possible conditions to operate on a daily basis!

We want to keep everyone that will be impacted by these projects over the coming years as informed and updated on every phase of construction.

Check in right here for the most current information on every phase of our capital improvement projects! 

RWY 5-23 Rehabilitation Project: Phase II

Click the image to the right to download the full presentation for Phase II, Sections A, B & C.

 

Work is expected to begin in the Fall of 2019 and continue in the Spring of 2020. Dates are subject to change and will be updated as new information becomes available.

RWY 13-31 Keel Work - October 2019: Completed

The Airport repaved approximately 1,000 feet of the keel of Runway 13/31 west of Runway 5/23 on October 7th. Similar to previous keel projects at the Airport, the airport repaved the center 50 feet.

runway work

RWY 5-23 and Taxiway Alpha Work: September 17-20: Completed

Runway 5/23 will be CLOSED from 2300L to 0600L nightly from Monday, September 17th through Thursday, September 20th.

Runway 13-31 will remain OPEN during this closure.

Taxiway A will be CLOSED between Taxiway Bravo and Taxiway Echo from 2300L Wednesday, September 19th to 0600L Thursday, September 20th.

These closures are needed for required geotechnical work that is in preparation for the larger Runway 5-23 Rehabilitation Project.

523

RWY 13-31 Paving Work: Aug. 16-18: Completed

In preparation for the continued Runway 5-23 Rehabilitation Project, MMU has scheduled construction for Runway 13-31. This work will entail milling and paving an overlay of 2,000 feet.

RWY 13-31 Work COMPLETED


MMU will be CLOSED to fixed-wing traffic aircraft on Sat. Aug. 18th from 0800L-0900L for painting the intersection of both runways

Runway 5/23 will be CLOSED Sat. August 18th from 0900L to 1400L

RWY 13-31 will remain OPEN during this closure

patched